Schedule Updates

Major construction on the Albany Avenue project began in June 2017 and is anticipated to be completed in Fall 2019. All travel lanes on Albany Ave. will remain open before 9am and after 3pm. During other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead/Westbourne. Hartford Police will be on hand to assist motorists. Business access and pedestrian walkways will be maintained at all times. If you have access concerns, please call Kimberly Owens at (860) 263-8533. For detailed bi-weekly schedule updates, please see below:

Week of December 17, 2018

  • Installation of lighting, electrical wires and traffic signals will continue throughout the project area.
  • Steel erection of permanent traffic signals will begin at the intersection of Homestead and Albany and will continue east.
  • The new traffic signals at the Bravo/Woodland entrance are scheduled to be fully operational this week.

Week of December 10, 2018

  • Testing of new traffic signals at the Bravo Plaza/Woodland entrance will begin this week.
  • Installation of lighting, electrical wires and traffic signals will continue throughout the project area.

Week of December 3, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Asphalt paving will occur in various locations throughout the project area.
  • Installation of lighting and electrical wires will continue between Homestead and Edgewood. Traffic signal installation will also occur throughout the project area.
  • Installation of brick pavers will continue on the northwest corner of Albany and Woodland (in front of Artists Collective); between Cabot and Edgewood (near Bank of America); and also on the west side of Homestead.

Week of November 26, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Asphalt paving will occur in various locations throughout the project area.
  • Installation of lighting and electrical wires will continue between Homestead and Edgewood. Traffic signal installation will also occur throughout the project area.
  • Installation of brick pavers will continue on the northwest corner of Albany and Woodland (in front of Artists Collective); between Cabot and Edgewood (near Bank of America); and also on the west side of Homestead.

Week of November 19, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition will occur on the south side of Albany between Edgewood and Sigourney.
  • Installation of granite curb is to occur on the south side of Albany between Edgewood and Sigourney.
  • Installation of lighting and conduit will occur on the south side of Albany between Edgewood and Sigourney and also on Homestead south of Albany.
  • Installation of the concrete sidewalks and driveway aprons will occur on the north side of Albany between Blue Hills and Woodland and also on Homestead south of Albany.
  • Installation of brick pavers continues on the north side of Albany between Blue Hills and Woodland and also on Homestead south of Albany.
  • Electrical work will occur across Albany at Edgewood. Installation of electrical wires will be ongoing throughout the project area. Ornamental light installation continues between Adams and Edgewood.
  • No work will occur on Nov. 22nd or Nov. 23rd. Work will resume Nov. 26th.                                                     

Week of November 12, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition will occur on the south side of Albany between Edgewood and Sigourney and also on the west side of Homestead south of Albany.
  • Installation of granite curb will occur on the south side of Albany between Edgewood and Sigourney and also on the west side of Homestead south of Albany.
  • Installation of lighting and conduit will occur on the south side of Albany between Edgewood and Sigourney and also on Homestead south of Albany.
  • Installation of the concrete sidewalks and driveway aprons will occur on the north side of Albany between Blue Hills and Woodland and also on Homestead south of Albany.
  • Installation of brick pavers continues on the north side of Albany between Blue Hills and Woodland and also on Homestead south of Albany.
  • Electrical work will occur across Albany at Edgewood. Installation of electrical wires will be ongoing throughout the project area. Ornamental light installation continues between Adams and Edgewood.

Week of November 5, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Drainage work will occur on the east and west side of Blue Hills near the Albany Branch Library.
  • Installation of granite curb and concrete sidewalks continues on the west side of Homestead between Interstate Battery and Jiffy Car Wash; expect partial lane closures in this area.
  • Electrical work continues on the south side of Albany between Cabot and Edgewood near Bank of America. Electrical work will also occur across Albany near Tinker Realty and Rainbow Variety; expect partial lane closures between Woodland and Oakland.
  • Ornamental light installation continues between Homestead and Woodland. Installation of electrical wires will be ongoing throughout the project area.
  • Traffic signals at the Bravo Plaza/Woodland entrance will begin operating with flashing red and yellow lights.
  • Brick paver installation continues on the north side of Albany between Blue Hills and Woodland.
  • Asphalt paving will occur in various locations throughout the project area.

Week of October 29, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Installation of granite curb continues on the west side of Homestead (between Interstate Battery and Jiffy Car Wash).
  • Electrical work continues on the southwest corner of Albany and Homestead (near Jiffy Car Wash) and also on the south side of Albany between Cabot and Edgewood. Ornamental light installation continues between Homestead and Woodland.
  • Installation of brick pavers continues on the southeast corner of Albany and Homestead; the south side of Albany between Sterling and Cabot; and also on the north side of Albany in front of the Albany Branch Library and the Artists Collective.
  • Roadway reconstruction/paving is underway on the north side of Albany between Blue Hills and Woodland; expect partial lane closures within this area.
  • Driveway paving will occur on the north side of Albany between Baltimore and Adams.

Week of October 22, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Traffic signal foundation work will occur on the NE corner of Albany and Woodland.
  • Installation of concrete sidewalks and driveway aprons will occur on the SE corner of Albany and Homestead (near Route 44 Auto Sales) and also on the south side of Albany between Sterling and Cabot.
  • Installation of brick pavers will occur on the north side of Albany between Woodland and Blue Hills.
  • Electrical work will occur across Albany at Woodland and at Sterling. Installation of electrical wires will be ongoing throughout the project area.
  • Drainage work continues on Blue Hills north of Albany.                                                                           

Week of October 15, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Installation of granite curb continues on the SE corner of Albany and Homestead (near Route 44 Auto Sales).
  • Installation of lighting and conduit will occur on Woodland north of Albany (near Golden Krust) and also on the south side of Albany between Cabot and Edgewood.
  • Installation of the concrete sidewalks and driveway aprons will occur on the north side of Albany between Blue Hills and Woodland and also on the south side of Albany between Sterling and Cabot.
  • Installation of brick pavers will continue on the south side of Albany between Sterling and Cabot.
  • Electrical work will occur across Albany at Oakland. Installation of electrical wires will be ongoing throughout the project area.
  • Miscellaneous paving work will occur throughout the project area.
  • Fence and gate installation continues project-wide.