Schedule Updates

Major construction on the Albany Avenue project began in June 2017 and is anticipated to be completed in Fall 2019. All travel lanes on Albany Avenue will remain open before 9am and after 3pm. During other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead/Westbourne. Business access and pedestrian walkways will be maintained at all times. If you have access concerns or questions, please call Kimberli Owens at (860) 263-8533. For detailed bi-weekly schedule updates, please see below:

Week of October 14, 2019

  • 10/15/19, one-way directional changes will take effect on Sterling, Lenox, Cabot, and Edgewood streets.
  • Roadway paving of Albany and portion of sides streets between Homestead and Oakland continues. Paving is scheduled to be completed by 10/18/19. Due to weather conditions, roadway paving along Albany between Homestead and Oakland may continue into the week of 10/21/19.
  • Sidewalk and driveway ramp installation continues on the north side of Albany between Edgewood and Vine. 
  • Installation of conduit and light pole foundations continues on the north side of Albany between Edgewood and Vine.
  • Brick paver installation will occur on the north side of Albany between Edgewood and Vine.

Week of October 7, 2019

  • Nighttime roadway paving of Albany and portions of side-streets between Homestead and Oakland continues.
  • Sidewalk and driveway ramp reconstruction continues on the south side of Albany between Garden and Bedford and also on the north side of Albany between Edgewood and Vine. No additional demolition of sidewalks is scheduled this year.
  • Sign installation, traffic signal, and other electrical work continues in preparation for one-way directional changes on Sterling, Lenox, Cabot, and Edgewood Streets. 
  • Installation of conduit and light pole foundations continues on the north side of Albany between Edgewood and Vine.
  • Brick paver installation continues on the south side of Albany between Garden and Bedford. 
  • NEXT WEEK: 10/15/19, one-way directional changes will take effect on Sterling, Lenox, Cabot, and Edgewood.

Week of September 30, 2019

Special Note: Normal Work Hours: 7:00am – 5:00pm, Monday-Friday Milling/Paving Hours: 7:00pm – 5:00am, Sunday-Thurs.

  • Roadway milling and parking lot demolition begins Sunday night, 9/29/19.
  • Utility work, and other preparation for roadway paving, continues on Albany and side streets from Homestead to Oakland.
  • Roadway and parking lot paving is scheduled to begin 10/2/2019. Preliminary paving will occur on Albany and side streets from Homestead to Oakland.
  • Installation of conduit and light pole foundations continues on the south side of Albany between Garden and Bedford and also on the north side of Albany between Edgewood and Vine.
  • Sidewalk installation continues on the south side of Albany between Garden and Bedford.
  • Brick paver installation continues on the south side of Albany and Magnolia.

Week of September 23, 2019*

  • Sidewalk reconstruction continues on the north side of Albany between Edgewood and Vine. 
  • Concrete bus pads installation continues on Albany between Homestead and Oakland. Expect partial lane closures. 
  • Utility work, and other preparation for roadway paving, will occur on Albany and side streets from Homestead to Oakland. Roadway milling will begin Sunday night (9/29) from 7pm to 5am.
  • Installation of granite curb will occur on the north side of Albany between Edgewood and Vine. Expect partial lane closures around the construction zone.
  • Installation of conduit and light pole foundations continues on the south side of Albany between Garden and Bedford and also on the north side of Albany between Edgewood and Vine.
  • Traffic signal foundation installation and other electrical work continues on the southwest corner of Garden and Albany.
  • Brick paver installation continues on the south side of Albany between Irving and Garden and also at the Burton intersection.

Week of September 16, 2019

  • Sidewalk demolition continues on the north side of Albany between Edgewood and Vine.
  • Installation of granite curb will occur on the north side of Albany between Edgewood and Vine. Expect partial lane closures around the construction zone.
  • Installation of conduit and light pole foundations continues on the south side of Albany between Garden and Bedford. 
  • Concrete bus pad installation continues on Albany between Homestead and Oakland. Expect partial lane closures within the area.
  • Mast arm foundation installation will begin at the intersection of Garden and Albany.
  • Concrete sidewalks and driveway aprons will be installed on the south side of Albany between Irving and Bedford.
  • Brick paver installation continues on the south side of Albany between Garden and Bedford.
  • Parking lot reconstruction will occur at the northeast corner of Deerfield and Albany.

Week of September 9, 2019

  • Sidewalk demolition will occur on the north side of Albany between Edgewood and Vine. 
  • Concrete bus pads will be installed on Albany between Homestead and Oakland. Expect partial lane closures within the area. 
  • Installation of granite curb will occur on the north side of Albany between Edgewood and Vine. Expect partial lane closures around the construction zone.
  • Installation of conduit and light pole foundations continues on the south side of Albany between Garden and Bedford. 
  • New traffic signals will be installed at the intersection of Edgewood and Albany.
  • Concrete sidewalks and driveway aprons will be installed on the south side of Albany between Irving and Garden.
  • Brick paver installation continues on the south side of Albany between Irving and Garden.
  • Installation of fencing/gates will occur on the south side of Albany between Woodland and Oakland.

Week of September 2, 2019

  • Sidewalk demolition will occur on the north side of Albany between Edgewood and Vine.
  • Concrete bus pad installation continues on Albany between Homestead and Oakland. Expect partial lane closures within the area.
  • Installation of granite curb continues on the south side of Albany between Garden and Bedford and also on the north side of Albany between Edgewood and Vine. Expect partial lane closures around the construction zone.
  • New traffic signals at the intersection of Oakland and Albany will be fully operational before the end of the week.
  • Installation of conduit and light pole foundations continues on the south side of Albany between Magnolia and Bedford.
  • Installation of brick pavers continues on the south side of Albany between Irving and Bedford.

Week of August 26, 2019

  • Sidewalk demolition will occur on the south side of Albany between Garden and Bedford. Preparation for sidewalk demolition (saw-cutting) will occur on the north side of Albany between Edgewood and Vine.
  • Concrete sidewalks and driveway aprons will be installed on the south side of Albany between Irving and Garden.
  • Concrete bus pads will be installed on Albany between Homestead and Oakland. Expect partial lane closures within the area. 
  • Installation of granite curb will occur on the south side of Albany between Garden and Bedford. Expect partial lane around the construction zone.
  • Installation of conduit and light pole foundations continues on the south side of Albany between Magnolia and Garden. 
  • New traffic signals at the intersection of Oakland and Albany will operate on flash this week. Traffic signal installation continues at the intersections of Burton and Magnolia.

Week of August 19, 2019

  • Sidewalk demolition will occur on the north side of Albany between Edgewood and Vine and also on the south side of Albany between Garden and Bedford. New concrete sidewalks will be installed on the south side of Albany between Irving and Garden.
  • Installation of granite curb will occur on the south side of Albany between Garden and Edgewood.
  • Installation of conduit and light pole foundations will occur on the north side of Albany between Edgewood and Sigourney, and will continue on the south side of Albany, east of Magnolia. 
  • Traffic signals will be installed at the intersections of Vine/Burton and Magnolia.
  • Bus pad installation continues on Albany east of Homestead.

Week of August 12, 2019

  • Preparation for sidewalk demolition will occur on the south side of Albany between Garden and Bedford and also on the north side of Albany between Edgewood and Vine. Sidewalk access will be maintained. Expect partial lane closures within the area.
  • Installation of conduit and light pole foundations heads east on the south side of Albany between Magnolia and Irving.
  • The new traffic lights at the Kent and Albany intersection will become fully operational this week.
  • Concrete sidewalks and driveway aprons will be installed on the south side of Albany between Sigourney and Magnolia.
  • Concrete bus pads will be installed on Albany between Homestead and Oakland. Expect partial lane closures within the construction area.  
  • Driveway paving will occur in various locations between Woodland and Burton.
  • Installation of brick pavers continues on the north side of Albany between Lenox and Edgewood.
Loading...