Schedule Updates

Major construction on the Albany Avenue project begins in June/July 2017 and is anticipated to be completed in Spring 2019. For detailed bi-weekly schedule updates, please see below:

Week of February 26, 2018

• Miscellaneous work is scheduled to be performed on newly installed drainage structures (project-wide)

Week of February 19, 2018

• The project field office will be closed on President’s Day, Monday, February 19th.

• Project coordination and planning continue in preparation for upcoming construction work.

Week of February 12, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Miscellaneous work is scheduled to be performed on newly installed drainage structures (project-wide).

Week of February 5, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Project coordination and planning continue in preparation for upcoming construction work.

Week of January 29, 2018*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Miscellaneous work is scheduled to be performed on newly installed drainage structures (project-wide).

Week of January 22, 2018*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Miscellaneous work is scheduled to be performed on newly installed drainage structures (project-wide).

Week of January 15, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

· Miscellaneous work will be performed on newly installed drainage structures (project-wide).

Week of January 8, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

· A brick paver mock-up is tentatively scheduled to be installed on the south side of Albany Avenue in front of AutoZone.
· Miscellaneous work will be performed on newly installed drainage structures (project-wide).

Schedule: Week of January 1, 2018*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• No construction work will occur on Monday, January 1, 2018. Work is scheduled to commence on Tuesday, January 2, 2018.
• Installation of temporary lighting will continue on both sides of Albany Avenue between Homestead Avenue and Baltimore Street.

Schedule: Week of December 25, 2017*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• No construction work will occur Monday-Tuesday, December 25-26, 2017. Work is scheduled to commence on Wednesday, December 27, 2017.
• A brick paver mock-up is tentatively scheduled to be installed on the south side of Albany Avenue in front of AutoZone.

Loading...