Schedule Updates

Major construction on the Albany Avenue project began in June 2017 and is anticipated to be completed in Fall 2020. All travel lanes on Albany Avenue will remain open before 9am and after 3pm. During other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead/Westbourne. Business access and pedestrian walkways will be maintained at all times. If you have access concerns or questions, please call Kimberli Owens at (860) 263-8533. For detailed bi-weekly schedule updates, please see below:

Week of 6/12/17 7am-3:30pm

• The contractor continues to survey from Blue Hills Avenue heading east. • The contractor excavates to identify utilities • Utility mark-outs continue. • Construction of the contractor area continues at 439-455 Homestead Avenue • Tree removal begins from Homestead Avenue heading east. • Temporary construction signs are to be installed. *All activities subject to weather

Week of 6/5/17 7am-3:30pm

• Contractor continues to survey the project area.
• A private company continues to mark-out utilities.
• Construction of the Contractor Area begins at 439-455 Homestead Avenue.
• Contractor starts the Project Documentation Video.
• Tree removal begins.

Week of 5/29/17 7am-3:30pm

• Contractor continues to survey the project area.
• A private company continues to mark-out utilities.
• Construction of the Contractor Area begins at 439-455 Homestead Avenue.
• Contractor starts the Project Documentation Video.

Week of 5/22/17 7am-3:30pm

Survey continues
Utility Mark Outs – Private Locator
Utility Coordination
Laydown Stage Area Planning

Week of 5/14

Survey
Tree Assessment with City of Hartford
Construction Inspection Field Office Set Up
Install Temporary Construction Signs

5/18 Public Information Meeting 5pm-7pm
The Chrysalis Center
255 Homestead Avenue
Hartford, CT 06112

Week of 5/8 7am – 3:30pm

Survey
Pre-construction Documentation – video
Mark Out Utilities
Field Office set up continues
Project Construction Sign Installation

Week of 5/1 – 7am to 3:30pm

Survey planning
Pre-Construction Documentation
Mark out Utilities
Field Office set up
Construction Sign Planning

Schedule (Weeks of 4/15-5/1)

Week of 4/17
No Field Work
Field Office Established – keys provided to project staff
Utility Meeting
Contractor submittals reviews and approvals continue

Week of 4/10
No Field Work
Contractor Submittal Reviews

Week of 4/7
Pre-construction meeting with CTDOT, Contractor, Inspection Team and others