Schedule Updates

Major construction on the Albany Avenue project begins in June/July 2017 and is anticipated to be completed in Spring 2019. For detailed bi-weekly schedule updates, please see below:

Week of January 15, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

· Miscellaneous work will be performed on newly installed drainage structures (project-wide).

Week of January 8, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

· A brick paver mock-up is tentatively scheduled to be installed on the south side of Albany Avenue in front of AutoZone.
· Miscellaneous work will be performed on newly installed drainage structures (project-wide).

Schedule: Week of January 1, 2018*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• No construction work will occur on Monday, January 1, 2018. Work is scheduled to commence on Tuesday, January 2, 2018.
• Installation of temporary lighting will continue on both sides of Albany Avenue between Homestead Avenue and Baltimore Street.

Schedule: Week of December 25, 2017*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• No construction work will occur Monday-Tuesday, December 25-26, 2017. Work is scheduled to commence on Wednesday, December 27, 2017.
• A brick paver mock-up is tentatively scheduled to be installed on the south side of Albany Avenue in front of AutoZone.

Week of December 17, 2017

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• General preparation for winter conditions will occur project-wide.
• Installation of decorative light pole foundations and conduit will continue on both sides of Albany Avenue between Homestead Avenue and Kent Street.
• A brick paver mock-up is scheduled to be installed on Albany Avenue in front of AutoZone.

Week of December 11, 2017

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Curbside and temporary paving will occur on the both sides of Albany Avenue between Homestead Avenue and Bedford Street.
• Construction of new concrete sidewalks, on the south side of Albany Avenue, west of Homestead Avenue, is scheduled to be completed this week.
• Installation of decorative light pole foundations and conduit will continue on both sides of Albany Avenue between Homestead Avenue and Kent Street.

Schedule: Week of November 27, 2017*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Curbside paving will occur on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Grading will occur along the sidewalk on the west side of Westbourne Parkway and the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Line-striping of the roadway is scheduled to occur on Homestead Avenue.
• Construction of new concrete driveway ramps and sidewalk will continue on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Installation of conduit will occur on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Drainage work will continue, on both sides of Albany Avenue (project-wide), which includes silt sack removal, catch basin finishing, and installation of trap hoods.
• Utility Work Scheduled: Comcast (Albany Avenue west of Baltimore Street).

Schedule: Week of December 4, 2017*
Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Curbside paving will occur on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Grading will occur along the sidewalk on the west side of Westbourne Parkway and the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Line-striping of the roadway is scheduled to occur on Homestead Avenue.
• Construction of new concrete driveway ramps and sidewalk will continue on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Installation of conduit will occur on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Drainage work will continue, on both sides of Albany Avenue (project-wide), which includes silt sack removal, catch basin finishing, and installation of trap hoods.
• Utility Work Scheduled: Comcast (Albany Avenue west of Baltimore Street).

*weather permitting

Schedule: Week of November 20, 2017*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Drainage work will continue on both sides of Albany Avenue east of Sigourney Street.
• Installation of conduit will occur across the intersection of Albany Avenue and Homestead Avenue.
• Granite curb installation will continue on the west side of Homestead Avenue.
• Construction of new concrete sidewalk will continue on the south side of Albany Avenue west of Homestead Avenue.
• Installation of full-depth roadway patches will continue between Homestead Avenue and Bedford Street.

• The contractor has tentatively scheduled catch basin silt sack insert removal and catch basin parging (repairs) for Wednesday (11/22) with normal work hours of 7:00am-5:00pm.
• There will be no construction work this Thursday (11/23) or Friday (11/24).
• Normal work hours will resume next Monday (11/27) at 7:00am.

Schedule: Week of November 13, 2017*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Roadway paving, for the widening of the roadway, will occur on the east side of Homestead Avenue.
• Drainage work will continue on both sides of Albany Avenue east of Sigourney Street.
• Installation of conduit will occur across the intersection of Albany Avenue and Homestead Avenue.
• Granite curb installation will continue on the west side of Westbourne Parkway/Homestead Avenue and on the south side of Albany Avenue west of Homestead Avenue.
• Construction of new concrete driveway ramps and sidewalk will continue on the east side of Homestead Avenue and on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Installation of full-depth roadway patches is scheduled to begin between Homestead Avenue and Bedford Street.
• Utility Work Scheduled: Eversource (Blue Hills Avenue), CNG (Sterling Street) and Comcast (Albany Avenue west of Baltimore Street).

Week of November 6, 2017

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Survey will continue on Albany Avenue between Homestead Avenue and Bedford Street to identify locations for drainage structures and granite curb.
  • Drainage work will continue on both sides of Albany Avenue east of Oakland Terrace.
  • Installation of light pole foundations, conduit, and temporary illumination will occur on Homestead Avenue, Westbourne Parkway, and on the south side of Albany Avenue, west of Homestead Avenue.
  • Granite curb installation will continue on Homestead Avenue and will continue on the south side of Albany Avenue, west of Homestead Avenue.
  • Eversource is scheduled to perform utility work on Blue Hills Avenue.
  • Roadway grading, for the widening of the roadway, will occur on Homestead Avenue.
  • Construction of new concrete driveway ramps will commence this week on Homestead Avenue.
  • Saw cutting of the roadway, for the installation of drainage structures and curb-line will continue on both sides of Albany Avenue between Homestead Avenue and Bedford Street.
  • Installation of full-depth roadway patches will continue between Homestead Avenue and Bedford Street.