Schedule Updates

Major construction on the Albany Avenue project begins in June/July 2017 and is anticipated to be completed in Spring 2019. For detailed bi-weekly schedule updates, please see below:

Week of June 18, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition of existing curb/sidewalks will occur on the north side of Albany between Westbourne and Baltimore and will continue east.
  • Installation of light pole foundations, conduit, and temporary lighting will continue on Woodland.
  • Traffic signal foundation work continues near the Bravo Plaza Woodland Entrance and will begin at the corner of Blue Hills and Albany and also at Oakland and Albany.
  • Concrete wall construction continues on the NW corner of Albany and Woodland.
  • Brick paver installation continues east on the south side of Albany between Kent and Woodland.

Week of June 11, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Installation of light pole foundations, conduit, and temporary lighting continues on Woodland and on the south side of Albany to Oakland.
  • Traffic signal foundation work continues near the Bravo Plaza Woodland Entrance.
  • Roadway reconstruction and asphalt installation will occur on Baltimore, Woodland, and also on the south side of Albany between Milford and Woodland.
  • Installation of concrete sidewalks and driveway aprons will occur on the east side of Woodland and on the south side of Albany between Milford and Oakland.
  • Brick paver installation continues east on the south side of Albany between Kent and Woodland.
  • Concrete bus pad construction will occur on the south side of Albany between the Bravo Plaza Entrance and Woodland.

Week of June 4, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition of existing curb/sidewalks and installation of new granite curb continues on the north side of Albany between Westbourne and Baltimore and will continue east on the south side of Albany from Oakland to Sterling.
  • Installation of light pole foundations, conduit, and temporary lighting will continue on the south side of Albany to Oakland.
  • Concrete wall construction continues on the NW corner of Albany & Woodland.
  • Installation of new concrete sidewalks and driveway ramps continues on Woodland between Albany and the Bravo Entrance.
  • Brick paver installation continues east on the south side of Albany between Kent and Woodland.
  • Roadway reconstruction and asphalt installation will occur on Baltimore and also on the south side of Albany between Milford and Woodland.

Week of May 29, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition of existing curb/sidewalks and installation of new granite curb will begin on the north side of Albany between Westbourne and Baltimore and will continue east on the south side of Albany from Oakland to Sterling.
  • Installation of light pole foundations, conduit, and temporary lighting continues on Woodland and on the south side of Albany to Oakland.
  • Traffic signal foundation work continues on the SE corner of Milford and at the Bravo Plaza Woodland Entrance.
  • Concrete wall construction continues on the NW corner of Albany and Woodland.
  • Installation of concrete sidewalks and driveway aprons will continue east on Albany between Milford and Woodland. Preparation for sidewalk installation will occur on the east side of Woodland.
  • Brick paver installation continues east on the south side of Albany between Kent and Woodland.
  • Concrete bus pad construction will occur on the south side of Albany between the Bravo Plaza Entrance and Woodland.

Week of May 21, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition of existing curb/sidewalks and installation of new granite curb will occur on the south side of Albany Avenue between Woodland & Oakland Terrace.
  • Installation of light pole foundations, conduit, and temporary lighting will occur on both sides of Albany between Blue Hills & Woodland.
  • Traffic signal foundation installation continues at the Bravo Plaza Woodland Entrance, SE Kent & SE Milford.
  • Concrete wall construction continues on the NW corner of Albany & Woodland.
  • Installation of new concrete sidewalks and driveway ramps continues on the south side of Albany between Baltimore & Milford.
  • Brick paver installation will continue on the south side of Albany between Baltimore and Milford.
  • Roadway reconstruction continues at the Bravo Plaza Albany Entrance and will begin on Baltimore and on the east side of Woodland between Albany and the Bravo Plaza Woodland Entrance.
  • Asphalt installation will occur on Baltimore and between the Bravo Plaza Albany entrance and Woodland.

Week of May 14, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition of existing curb/sidewalks and installation of new granite curb will occur on the south side of Albany Avenue between Woodland & Oakland Terrace.
  • Installation of light pole foundations, conduit, and temporary lighting will occur on Woodland between Albany and the Bravo Plaza Woodland Entrance.
  • Traffic signal foundation installation will begin at the Bravo Plaza Woodland Entrance, SE Kent & SE Milford.
  • Concrete wall construction continues on the NW corner of Albany & Woodland.
  • Installation of new concrete sidewalks and driveway ramps continues on the south side of Albany between Baltimore & Milford.
  • Brick paver installation continues on the south side of Albany between Baltimore & Milford.

Week of May 7, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Installation of new concrete sidewalks and driveway ramps continues on the south side of Albany between Baltimore and Milford.
  • Installation of new granite curb will continue on Woodland between Albany and the Woodland Bravo Plaza Entrance.
  • Installation of light pole foundations, conduit, and temporary lighting will occur on both sides of Albany between Blue Hills and Woodland.
  • Concrete wall construction continues at the corner of Albany and Woodland.
  • Bravo Plaza entrance construction continues on the south side of Albany. 
  • Brick paver installation will continue on the south side of Albany between Baltimore and Milford.

Week of April 30, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Installation of new concrete sidewalks and driveway ramps continues on the south side of Albany between Baltimore and Milford.
  • Demolition of existing curb/sidewalks and installation of new granite curb will continue on Woodland between Albany and the Woodland Bravo Plaza Entrance.
  • Installation of light pole foundations, conduit, and temporary lighting will occur on both sides of Albany between Blue Hills and Woodland.
  • Concrete wall construction continues at the corner of Albany and Woodland.
  • Bravo Plaza entrance construction/road widening continues on the south side of Albany.
  • Brick paver installation will continue on the south side of Albany between Baltimore and Milford.

Week of April 23 , 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

•Installation of planter curb will continue on the south side of Albany and will continue east.
•Brick paver installation will continue on the south side of Albany, east of Milford.
•Demolition of existing curb/sidewalks/driveway ramps and installation of new granite curb, concrete sidewalks and driveway ramps will continue on Westbourne and on the south side of Albany, east of Milford.
•Installation of light pole foundations, conduit, and temporary lighting will occur on both sides of Albany between Homestead and Blue Hills.
•Retaining Wall Construction on Woodland Street.
•Bravo Entrance Construction will continue on south side of Albany.

Week of April 16, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Installation of planter curb will continue on the south side of Albany, east of Homestead.
  • Brick paver installation will continue east of Homestead on the south side of Albany.
  • Demolition of existing curb/sidewalks/driveway ramps and installation of new granite curb, concrete sidewalks and driveway ramps will continue on the south side of Albany, east of Milford.
  • Installation of light pole foundations, conduit, and temporary lighting will occur on both sides of Albany between Homestead and Blue Hills.
  • Retaining Wall Construction on Woodland Street.
  • Bravo Entrance construction to start on south side of Albany.