Schedule Updates

Major construction on the Albany Avenue project began in June 2017 and is anticipated to be completed in Fall 2019. All travel lanes on Albany Ave. will remain open before 9am and after 3pm. During other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead/Westbourne. Hartford Police will be on hand to assist motorists. Business access and pedestrian walkways will be maintained at all times. If you have access concerns, please call Kimberly Owens at (860) 263-8533. For detailed bi-weekly schedule updates, please see below:

Week of January 21, 2019

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday
  • Traffic signal foundation installation will occur on the northeast corner of Albany and Woodland in front of Golden Krust Bakery.
  • Steel erection of permanent traffic signals will occur at the Bravo Plaza entrance on Woodland. Partial lane closures may occur near the intersection. Expect minimal traffic delays.
  • Installation of electrical wires will continue on Woodland and on Albany between Westbourne and Sterling. 

Week of January 14, 2019

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday
  • Traffic signal work will occur on Albany, west of Westbourne, at the intersections of Prospect, Bloomfield, Scarborough, and Mark Twain. Signal work will also occur on Albany, east of Bedford, at the intersection of Brook. Minimal traffic delays may occur.
  • Electrical work will also occur on the northwest corner of Albany and Blue Hills near Melanin boutique.

Week of January 7, 2019

• Installation of electrical wires for traffic signals continues on Albany Avenue between Kent and Sterling.

Week of December 31, 2018

  • No construction work will occur on Tuesday, January 1st.
  • Installation of lighting and electrical wires continues throughout the project area.
  • Installation of permanent traffic signals continues between Homestead and Edgewood.

Week of December 24, 2018

  • No construction work will occur on Monday, December 24th or Tuesday, December 25th.
  • Installation of lighting and electrical wires continues throughout the project area.
  • Installation of permanent traffic signals will occur from the intersection of Homestead and Albany and will continue east toward Edgewood.

Week of December 17, 2018

  • Installation of lighting, electrical wires and traffic signals will continue throughout the project area.
  • Steel erection of permanent traffic signals will begin at the intersection of Homestead and Albany and will continue east.
  • The new traffic signals at the Bravo/Woodland entrance are scheduled to be fully operational this week.

Week of December 10, 2018

  • Testing of new traffic signals at the Bravo Plaza/Woodland entrance will begin this week.
  • Installation of lighting, electrical wires and traffic signals will continue throughout the project area.

Week of December 3, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Asphalt paving will occur in various locations throughout the project area.
  • Installation of lighting and electrical wires will continue between Homestead and Edgewood. Traffic signal installation will also occur throughout the project area.
  • Installation of brick pavers will continue on the northwest corner of Albany and Woodland (in front of Artists Collective); between Cabot and Edgewood (near Bank of America); and also on the west side of Homestead.

Week of November 26, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Asphalt paving will occur in various locations throughout the project area.
  • Installation of lighting and electrical wires will continue between Homestead and Edgewood. Traffic signal installation will also occur throughout the project area.
  • Installation of brick pavers will continue on the northwest corner of Albany and Woodland (in front of Artists Collective); between Cabot and Edgewood (near Bank of America); and also on the west side of Homestead.

Week of November 19, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition will occur on the south side of Albany between Edgewood and Sigourney.
  • Installation of granite curb is to occur on the south side of Albany between Edgewood and Sigourney.
  • Installation of lighting and conduit will occur on the south side of Albany between Edgewood and Sigourney and also on Homestead south of Albany.
  • Installation of the concrete sidewalks and driveway aprons will occur on the north side of Albany between Blue Hills and Woodland and also on Homestead south of Albany.
  • Installation of brick pavers continues on the north side of Albany between Blue Hills and Woodland and also on Homestead south of Albany.
  • Electrical work will occur across Albany at Edgewood. Installation of electrical wires will be ongoing throughout the project area. Ornamental light installation continues between Adams and Edgewood.
  • No work will occur on Nov. 22nd or Nov. 23rd. Work will resume Nov. 26th.                                                     