Week of June 8, 2020

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday*

  • Landscaping continues throughout the project limits.
  • Installation of electrical conduit and decorative lighting continues on the north side of Albany Avenue between Vine and Magnolia Streets.
  • Curbside, electrical trench, and parking lot paving will occur in various locations.
  • Sidewalk installation continues between Magnolia and Vine Streets on the north side of Albany Avenue.
  • Brick paver installation continues between Irving and Magnolia Streets on the north side of Albany Avenue.
  • Fencing installation continues in various locations.

*weather permitting