Schedule: Week of November 27, 2017*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Curbside paving will occur on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Grading will occur along the sidewalk on the west side of Westbourne Parkway and the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Line-striping of the roadway is scheduled to occur on Homestead Avenue.
• Construction of new concrete driveway ramps and sidewalk will continue on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Installation of conduit will occur on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Drainage work will continue, on both sides of Albany Avenue (project-wide), which includes silt sack removal, catch basin finishing, and installation of trap hoods.
• Utility Work Scheduled: Comcast (Albany Avenue west of Baltimore Street).

Schedule: Week of December 4, 2017*
Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Curbside paving will occur on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Grading will occur along the sidewalk on the west side of Westbourne Parkway and the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Line-striping of the roadway is scheduled to occur on Homestead Avenue.
• Construction of new concrete driveway ramps and sidewalk will continue on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Installation of conduit will occur on the south side of Albany Avenue between Homestead Avenue and Baltimore Street.
• Drainage work will continue, on both sides of Albany Avenue (project-wide), which includes silt sack removal, catch basin finishing, and installation of trap hoods.
• Utility Work Scheduled: Comcast (Albany Avenue west of Baltimore Street).

*weather permitting