Week of 8/21/17 7am-5pm

Allowable Work Hours: 7:00am – 5:00pm, Monday-Friday
• Test pits will be excavated to identify utilities in preparation for mast arm foundation and drainage structure installations.
• Survey will continue this week on Albany Avenue from Homestead Avenue to Bedford Street, to identify locations for decorative light and traffic controller foundations, drainage structures and new granite curbs.
• Saw cutting of the roadway, for the installation of drainage structures and removal of existing granite curb, will continue on Woodland Street as well as the north and south sides of Albany Avenue from Adams Street to Woodland Street.
• Installation of the drainage system will continue on Albany Avenue and all side roads from Westbourne Parkway to Woodland Street.
• Drainage work has progressed enough, so that the installation of the new granite curbs, sidewalks and brick pavers can commence. This work is the first step in the beautification of the Albany Avenue neighborhood, and is anticipated to commence August 23rd on Homestead Avenue.