Week of 9/18/17 7am-3:30pm

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday
• Survey will continue on Albany Avenue from Homestead Avenue to Bedford Street. Survey will be identifying locations for decorative light and traffic controller foundations, drainage structures and new granite curbs.
• Saw cutting of the roadway, for the installation of drainage structures, will continue on the north side of Albany Avenue between Blue Hills Avenue and Woodland Street.
• Installation of the drainage system will continue on the north side of Albany Avenue between Blue Hills Avenue and Woodland Street. Drainage work is also scheduled to commence at the Albany Avenue entrance road to the Bravo Plaza. This will involve alternating one-way traffic on the entrance roadway from 9:00 AM to 3:00 PM.
• Installation of light pole foundations and temporary illumination is scheduled to commence on Homestead Avenue.
• Eversource and Charter Oak Utilities will perform utility work on the northeast corner of Albany Avenue and Kent Street.