Week of 9/25/17 7am-3:30pm

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday
• Survey will continue on Albany Avenue from Homestead Avenue to Bedford Street. Survey will be identifying locations for decorative light and traffic controller foundations, drainage structures and new granite curbs.
• Installation of the drainage system will continue on the north side of Albany Avenue between Blue Hills Avenue and Woodland Street. Drainage work is also scheduled to continue on the Albany Avenue entrance road to the Bravo Plaza. This will involve alternating one-way traffic on the entrance roadway from 9:00 AM to 3:00 PM.
• Installation of light pole foundations and temporary illumination will continue this week on Homestead Avenue.
• Eversource and Charter Oak Utilities will perform utility work on the northeast corner of Albany Avenue and Woodland Street.
• Installation of the new granite curb on the east side of Homestead Avenue is anticipated to begin this week.