Week of December 11, 2017

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Curbside and temporary paving will occur on the both sides of Albany Avenue between Homestead Avenue and Bedford Street.
• Construction of new concrete sidewalks, on the south side of Albany Avenue, west of Homestead Avenue, is scheduled to be completed this week.
• Installation of decorative light pole foundations and conduit will continue on both sides of Albany Avenue between Homestead Avenue and Kent Street.