Week of October 16, 2017*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

• Survey will continue on Albany Avenue from Homestead Avenue to Bedford Street. Survey will be identifying locations for decorative light and traffic controller foundations, drainage structures and new granite curbs.
• Installation of the drainage system will continue on both sides of Albany Avenue east of Woodland Street.
• Installation of light pole foundations, conduit, and temporary illumination will occur on the north side of Albany Avenue (west of Homestead Avenue), on both sides of Homestead Avenue, and on the west side of Westbourne Parkway.
• Installation of the new granite curb will continue on the east side of Homestead Avenue and will begin on the south side of Albany Avenue, west of Homestead Avenue.

*weather permitting