Week of 9/11/17

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday
• Survey will continue this week on Albany Avenue from Homestead Avenue to Bedford Street, to identify locations for decorative light and traffic controller foundations, drainage structures and new granite curbs.
• Saw cutting of the roadway, for the installation of drainage structures and removal of existing granite curb, will continue on the north and south sides of Albany Avenue.
• Installation of the drainage system will continue on Albany Avenue and all side roads from Westbourne Parkway to Woodland Street.
• Installation of the light pole foundations and light poles is anticipated to commence this week on Homestead Avenue.