Week of April 8, 2019

  • Demolition of existing curb/sidewalks will begin on the south side of Albany between Edgewood and Sigourney and also on the north side of Albany between Oakland and Deerfield.
  • Saw cutting of the roadway will occur on the north side of Albany between Oakland and Lenox.
  • Drainage and utility work will resume at the NW corner of Albany and Blue Hills. 
  • Granite curb installation will occur on the north side of Albany between Woodland and Oakland.
  • Installation of light pole foundations, conduit, and temporary illumination will occur on the north side of Albany between Woodland and Oakland.
  • Traffic signal foundation installation will begin on the NE Corner of Albany and Woodland and also on the SW corner of Albany and Edgewood.
  • Brick paver installation will resume at the intersection of Homestead and Albany and also on the south side of Albany between Cabot and Sigourney.