    • Demolition of existing curb/sidewalks will continue on the north side of Albany between Baltimore and Adams and will begin between Oakland and Sterling.
    • Installation of granite curb continues on the north side of Albany between Baltimore and Adams.
    • Installation of light pole foundations, conduit, and temporary lighting will occur on the north side of Albany between Westbourne and Baltimore.
    • Traffic signal foundation work continues at the intersection of Albany and Westbourne/Homestead and will also occur on the northwest corner of Kent.
    • Installation of new concrete sidewalks and driveway aprons continues on the north side of Albany between Westbourne and Kent.
  • Brick paver installation continues on Woodland (south of Albany).