Week of July 2, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • No construction will occur on Wednesday, July 4th. Normal work hours will resume on Thursday, July 5th.
  • Demolition of existing curb/sidewalks will continue on the north side of Albany from Kent to Baltimore.
  • Traffic signal foundation work continues at the intersection of Albany and Westbourne/Homestead.
  • Brick paver installation continues on the south side of Albany between Milford and Woodland and will continue southbound on Woodland.