Week of July 8, 2019

  • Roadway reconstruction will occur on the NE corner of Blue Hills and Albany. Expect partial lane closure in the work zone.
  • Bravo Plaza Albany entrance reconstruction continues. All Bravo Plaza merchants remain open for business. For McDonald’s access use Albany Avenue. For access to all other Bravo Plaza merchants use Woodland.
  • Installation of granite curb will begin on the south side of Albany between Burton and Magnolia and will continue at the Bravo Plaza Albany entrance. 
  • Installation of light pole foundations, conduit, and temporary illumination continues east on the south side of Albany and Burton. 
  • Installation of new street signs continues.
  • Sidewalk construction continues at the NE corner of Blue Hills.
  • Sidewalk installation will occur on the SE corner of Woodland.
  • Installation of brick pavers will occur on the south side of Albany between Edgewood and Sigourney, on the NW corner of Lenox, and also on the NW corner of Blue Hills.