Week of July 9, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition of existing curb/sidewalks will occur on the north side of Albany between Baltimore and Adams.
  • Installation of granite curb continues on the north side of Albany from Westbourne to Baltimore.
  • Installation of light pole foundations, conduit, and temporary lighting will occur on the north side of Albany between Westbourne and Baltimore.
  • Traffic signal foundation work continues at the intersection of Albany and Westbourne/Homestead.
  • Installation of new concrete sidewalks and driveway aprons continues on the south side of Albany between Woodland and Oakland and will also occur on the north side of Albany between Westbourne and Baltimore.
  • Brick paver installation continues on the south side of Albany between Milford and Woodland and will continue southbound on Woodland.
  • Preparation for paving of the lot at 992 Albany will begin.