Week of June 1, 2020

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday*

  • Landscaping continues throughout the project limits.
  • Sidewalk demolition will occur on the east side of Vine Street north of Albany Avenue.
  • Granite curb installation continues between Vine and Magnolia Streets on the north side of Albany Avenue.
  • Installation of electrical conduit and decorative lighting continues on the north side of Albany Avenue between Vine and Magnolia Streets.
  • Sidewalk installation will begin between Magnolia and Vine Streets on the north side of Albany Avenue.
  • Brick paver installation will occur between Irving and Magnolia Streets on the north side of Albany Avenue.
  • Fencing installation will occur in various locations.

*weather permitting

All travel lanes on Albany will remain open before 9am and after 3pm; during other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead and Westbourne. Hartford Police will assist motorists and pedestrians.