Week of June 22, 2020

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday*

Milling Hours: 7:00pm – 6:00am, Sunday-Friday*

  • Nighttime milling operations will begin Sunday (6/21/20) and are scheduled to end Friday morning (6/26/20). See flyer above for more information.
  • Sidewalk installation will occur on the north side of Albany Avenue between Vine and Magnolia Streets.
  • Granite curb installation will occur between Magnolia and Irving Streets on the south side of Albany Avenue and also at the intersection of Burton Street and Homestead Avenue.
  • Installation of electrical conduit and decorative lighting continues on the north side of Albany Avenue between Vine and Bedford Streets.
  • Curbside and electrical trench paving continues.
  • Parking lot reconstruction continues on Albany Avenue: Scotts’ Bakery (NE Adams), NE Deerfield and SE Edgewood.
  • Brick paver installation continues on the north side of Albany Avenue at Vine Street.
  • Concrete bus pad installation will occur on Albany Avenue between Deerfield and Magnolia Streets.
  • Traffic Impacts: Expect partial lane closures and minor delays during milling and paving, curb installation and concrete bus pad operations this week.

*weather permitting

All travel lanes on Albany will remain open before 9am and after 3pm; during other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead and Westbourne. Hartford Police will assist motorists and pedestrians.