Week of March 9, 2020

  • Drainage work will occur on the north side of Albany Avenue between Garden Street and Bedford Street.
  • Decorative lighting installation continues on Albany Avenue east of Edgewood Street.
  • Installation of granite curb will begin on the north side of Albany Avenue around the Vine Street intersection. Granite curb installation will continue east on the north side of Albany Avenue to Bedford Street.