Week of May 14, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition of existing curb/sidewalks and installation of new granite curb will occur on the south side of Albany Avenue between Woodland & Oakland Terrace.
  • Installation of light pole foundations, conduit, and temporary lighting will occur on Woodland between Albany and the Bravo Plaza Woodland Entrance.
  • Traffic signal foundation installation will begin at the Bravo Plaza Woodland Entrance, SE Kent & SE Milford.
  • Concrete wall construction continues on the NW corner of Albany & Woodland.
  • Installation of new concrete sidewalks and driveway ramps continues on the south side of Albany between Baltimore & Milford.
  • Brick paver installation continues on the south side of Albany between Baltimore & Milford.