Week of May 27, 2019

  • No construction work will occur on Memorial Day, 5/27.
  • Installation of light pole foundations, conduit, and temporary illumination continues on the north side of Albany between Lenox and Edgewood.
  • Conduit installation will continue across Albany between Woodland and Oakland. Expect partial lane closures in this area.
  • New concrete sidewalks/driveway aprons will be installed on the south side of Albany between Edgewood and Sigourney.
  • Preparation work for new sidewalks/driveway aprons continues on the north side of Albany between Deerfield and Lenox.
  • Brick paver installation will occur on the south side of Albany between Edgewood and Sigourney.
  • Looking Ahead… Installation of new traffic signs is tentatively scheduled to begin within the next few weeks.