Week of May 6, 2019

  • Drainage and utility work continues at the intersection of Blue Hills and Albany.
  • Installation of light pole foundations, conduit, and temporary illumination continues on the north side of Albany between Deerfield and Lenox and also on the south side of Albany between Edgewood and Sigourney.
  • New concrete sidewalks and driveway aprons will be installed on the north side of Albany between Woodland and Oakland.
  • Preparation work for new sidewalks and driveway aprons will occur on the north side of Albany between Oakland and Lenox.