Week of November 25, 2019

  • No construction work will occur on Thursday, November 28th. Limited construction activities may occur on Friday, November 29th.
  • General preparation for winter conditions continues project-wide.
  • Paving along the curb line will occur in various places along Albany and within the project area. Paving behind driveways and sidewalks will also occur in various locations. Expect partial lane closures near paving operations.
  • Concrete sidewalk, driveway aprons, and brick paver installation continues on the north side of Albany between Sigourney and Vine. Sidewalk reconstruction will also occur on the southwest corner of Burton and Albany.
  • Utility work continues near the southwest corner of Burton and Albany. Expect minor traffic delays near the Burton/Albany intersection.
  • Electrical work continues on the south side of Albany between Burton and Bedford and will also occur across the roadway at the Garden/Albany intersection. Expect partial lane closures near the Garden/Albany intersection.
  • Traffic signal operations will occur at intersections between Homestead and Edgewood.