Week of October 14, 2019

  • 10/15/19, one-way directional changes will take effect on Sterling, Lenox, Cabot, and Edgewood streets.
  • Roadway paving of Albany and portion of sides streets between Homestead and Oakland continues. Paving is scheduled to be completed by 10/18/19. Due to weather conditions, roadway paving along Albany between Homestead and Oakland may continue into the week of 10/21/19.
  • Sidewalk and driveway ramp installation continues on the north side of Albany between Edgewood and Vine. 
  • Installation of conduit and light pole foundations continues on the north side of Albany between Edgewood and Vine.
  • Brick paver installation will occur on the north side of Albany between Edgewood and Vine.