Week of October 29, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Installation of granite curb continues on the west side of Homestead (between Interstate Battery and Jiffy Car Wash).
  • Electrical work continues on the southwest corner of Albany and Homestead (near Jiffy Car Wash) and also on the south side of Albany between Cabot and Edgewood. Ornamental light installation continues between Homestead and Woodland.
  • Installation of brick pavers continues on the southeast corner of Albany and Homestead; the south side of Albany between Sterling and Cabot; and also on the north side of Albany in front of the Albany Branch Library and the Artists Collective.
  • Roadway reconstruction/paving is underway on the north side of Albany between Blue Hills and Woodland; expect partial lane closures within this area.
  • Driveway paving will occur on the north side of Albany between Baltimore and Adams.