Week of October 7, 2019

  • Nighttime roadway paving of Albany and portions of side-streets between Homestead and Oakland continues.
  • Sidewalk and driveway ramp reconstruction continues on the south side of Albany between Garden and Bedford and also on the north side of Albany between Edgewood and Vine. No additional demolition of sidewalks is scheduled this year.
  • Sign installation, traffic signal, and other electrical work continues in preparation for one-way directional changes on Sterling, Lenox, Cabot, and Edgewood Streets. 
  • Installation of conduit and light pole foundations continues on the north side of Albany between Edgewood and Vine.
  • Brick paver installation continues on the south side of Albany between Garden and Bedford. 
  • NEXT WEEK: 10/15/19, one-way directional changes will take effect on Sterling, Lenox, Cabot, and Edgewood.