Week of October 8, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Installation of granite curb will occur on the southeast corner of Albany and Homestead (near Route 44 Auto Sales).
  • Installation of lighting and conduit continues on Woodland, north of Albany. Installation of electrical wires will be ongoing throughout the project area.
  • Traffic signal foundation will occur on the northeast corner of Albany and Woodland.
  • Installation of concrete sidewalks and driveway aprons continues on north side of Albany between Blue Hills and Woodland and also on the south side of Albany between Sterling and Cabot.
  • Installation of brick pavers will occur on the north side of Albany between Blue Hills and Woodland and also on the south side of Albany between Oakland and Sterling.