Week of September 11, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition of existing curb/sidewalks will continue on the south side of Albany between Sterling and Cabot.
  • Installation of granite curb will continue on the south side of Albany between Sterling and Cabot and will begin on the northwest corner of Woodland (near Artists Collective).
  • Installation of lighting and conduit will occur on the south side of Albany between Sterling and Cabot and also on the northwest corner of Woodland.
  • Traffic signal foundation work continues at the intersection of Albany and Sterling. Installation of temporary traffic signals continues at the intersection of Albany and Blue Hills.
  • Electrical work will occur across Albany near Woodland.
  • Installation of concrete sidewalks and driveway aprons continues on south side of Albany between Oakland and Cabot.
  • Installation of brick pavers continues on the south side of Albany between Oakland and Cabot.
  • Drainage work will occur on the north side of Albany and Blue Hills.