Week of September 16, 2019

  • Sidewalk demolition continues on the north side of Albany between Edgewood and Vine.
  • Installation of granite curb will occur on the north side of Albany between Edgewood and Vine. Expect partial lane closures around the construction zone.
  • Installation of conduit and light pole foundations continues on the south side of Albany between Garden and Bedford. 
  • Concrete bus pad installation continues on Albany between Homestead and Oakland. Expect partial lane closures within the area.
  • Mast arm foundation installation will begin at the intersection of Garden and Albany.
  • Concrete sidewalks and driveway aprons will be installed on the south side of Albany between Irving and Bedford.
  • Brick paver installation continues on the south side of Albany between Garden and Bedford.
  • Parking lot reconstruction will occur at the northeast corner of Deerfield and Albany.