Week of September 4, 2018

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Demolition of existing curb/sidewalks will continue on the south side of Albany between Sterling and Cabot.
  • Installation of granite curb will occur on the south side of Albany between Sterling and Cabot.
  • Installation of temporary traffic signals will begin at the intersection of Albany and Blue Hills.
  • Electrical work will occur across Albany near Kent and Woodland.
  • Installation of concrete sidewalks and driveway aprons continues on the north side of Albany between Baltimore and Adams and also on the south side of Albany between Oakland and Sterling.
  • Installation of brick pavers continues on the north side of Albany between Baltimore and Adams and also on the south side of Albany between Oakland and Sterling.
  • Drainage work will occur on the north side of Albany and Woodland.