Week of September 9, 2019

  • Sidewalk demolition will occur on the north side of Albany between Edgewood and Vine. 
  • Concrete bus pads will be installed on Albany between Homestead and Oakland. Expect partial lane closures within the area. 
  • Installation of granite curb will occur on the north side of Albany between Edgewood and Vine. Expect partial lane closures around the construction zone.
  • Installation of conduit and light pole foundations continues on the south side of Albany between Garden and Bedford. 
  • New traffic signals will be installed at the intersection of Edgewood and Albany.
  • Concrete sidewalks and driveway aprons will be installed on the south side of Albany between Irving and Garden.
  • Brick paver installation continues on the south side of Albany between Irving and Garden.
  • Installation of fencing/gates will occur on the south side of Albany between Woodland and Oakland.