Week of September 28, 2020

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday*

  • Milling and paving operations may occur between 7:00pm-6:00am.
  • Roadway reconstruction continues on Vine Street, Irving Street, and also at the intersection of Burton Street and Homestead Avenue.
  • Sidewalk demolition continues on the east side of Vine Street near the Albany Avenue intersection.
  • Granite curb installation will begin on the east side of Vine Street near the Albany Avenue intersection.
  • Landscaping continues throughout the project limits.
  • Traffic signal installation is scheduled to begin at the northeast corner of Vine Street and Albany Avenue.
  • Bike post installation continues.
  • Traffic Impacts: Anticipate lane closures and detours during roadway reconstruction. Follow signs for pedestrian detours during sidewalk work. Minor traffic delays may occur.

*weather permitting

All travel lanes on Albany will remain open before 9am and after 3pm; during other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead and Westbourne. Hartford Police will assist with traffic.