Week of April 19, 2021

Normal Work Hours: 7:00am–5:00pm, MondayFriday*

  • Brick and sidewalk repair work is tentatively scheduled to occur this week in various locations throughout the project limits.
  • Planning and coordination to complete all contract and punch list work continues.
  • Traffic Impacts: Pedestrian detours may occur during sidewalk work.

LOOKING AHEAD: Topsoil placement and hydroseeding should resume within the next few weeks. Tree and landscaping review is in progress. Any trees or plantings that need to be replaced will be installed during this construction season.

*weather permitting