Week of November 16, 2020

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday*

  • Fence installation continues throughout the project limits.
  • Installation of traffic signals and other electrical work continues at the intersection of Albany Avenue and Vine Street.
  • Sidewalk reconstruction will be completed near the Bravo Plaza entrance on Albany Avenue and also on the south side of Albany Avenue between Oakland Terrace and Woodland Street.
  • Parking lot striping is scheduled to occur overnight at the Albany Avenue intersections of Adams Street and Magnolia Street.
  • Traffic Impacts: Anticipate pedestrian detours during sidewalk related construction this week.

*weather permitting

All travel lanes on Albany Avenue will remain open before 9am and after 3pm; during other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead Avenue and Westbourne Parkway. Hartford Police will assist with traffic.