Week of October 12, 2020

Schedule: Week of October 12, 2020*

Normal Work Hours: 7:00am – 5:00pm, Monday-Friday

  • Reconstruction of the southwest corner of Burton Street and Albany Avenue continues.
  • Hydroseeding and other landscaping will occur throughout the project limits.
  • Sidewalk demolition may occur this week near the NE corner of Vine Street and Albany Avenue.
  • Traffic Impacts: Anticipate partial lane closures during construction operations on Burton and Vine Streets. Minor traffic delays may occur in these areas.

*weather permitting

All travel lanes on Albany will remain open before 9am and after 3pm; during other hours, partial lane closures may occur. Traffic will be maintained in both directions on Homestead and Westbourne. Hartford Police will assist with traffic.